Heydar Aliyev Oil Refinery


Summary

Project: SOCAR Heydar Aliyev Oil Refinery Modernization and Reconstruction Project/ Package A-West Area General Construction works
Contractor: Tecnimont-KT Joint Venture (TCM-KT JV Azerbaijan)
Subcontractor: PROKON 
Location: Baku, Azerbaijan
Scope of Works: Steel Structure Erection, Piping Fabrication & Erection
General information: Client has initiated the rewamp and upgrade of the HAOR Refinery for facilities to be capable of processing 7.5 MMTPA of crude oil, while meeting quantity and quality requirements of products both to feed Azerikimya revamped petrochemical plant and to produce Euro V quality automative transportation fuels Equipment erection works, Electrical, Instrumentation, Painting, Insulation, Precomissioning works
Commencement date: October 2018
Planned Completion date: November 2020